Introduction
This is part of a series on the companies and thinking that have particularly influenced us.
For those of you who may not have come across it before, the Chaos Report was published by the Standish Group, a US-based research advisory organisation focusing on software development performance. It was first published in 1995, with regular updates and refreshes until its final publication in 2020. To our knowledge, it is unique as a study of 50,000 IT delivery projects across 1,000 organisations by the final publication; investigating which of 104 factors (24 organisational and 80 project related) correlated (or didn’t) with project success.
And although the last Chaos Report was published five years ago now, its findings are as valid today as they were then. It’s an invaluable resource of what does and doesn’t work based on real-world data; no opinions, no hypotheses, no sales pitches.
So we thought we’d capture some of our key takeaways from the final report:
- The top three factors for project success are all people-related, and the most valuable thing you can do as an organisation to increase the chances of your projects being successful is to invest in the soft skills of your teams and sponsors.
- Agile projects are more successful than waterfall projects, but it’s not a silver bullet. Dressing waterfall up as agile will actually reduce your chance of being successful. Breaking up big projects into a series of smaller projects is more likely to make you successful.
- Skills, tooling, and completeness of requirements are poor indicators of project success.
- If you can only improve one thing, improve your decision latency.
Definition of Success
In the following charts and commentary, the Chaos Report uses three measures of project success:
- Did it deliver on time
- Did it deliver to budget
- Did it deliver an outcome that was satisfactory to the customer
And then three definitions of project outcome:
- Successful – the project met all three measures of success
- Challenged – the project did not meet all three measures of success
- Failed – the project was cancelled or the product was never used
Takeaway 1 – people make projects successful
The Chaos report describes 6 key factors that show a significant correlation with whether the project was successful. The first three are all people-related – did the project have a good team, did it have a good sponsor, and was it operating in the right cultural environment?
The Good Team
The Good Team is the project’s workhorse. The sponsor breathes life into the project, but the team takes that breath and uses it to create a viable product that the organization can use and from which it derives value.
The first and most important factor (by quite a large margin) is whether there’s a good team. Projects with great teams have an 80% chance of success (meaning that they can overcome almost any other factor), and those with very poor teams have no chance of success:

But what do we mean by a “good team”? The Chaos Report has the evidence behind this – capturing 10 principles (described as a set of skills), and showing how each contributes to project success based on the evidence. We won’t list them all here (but will instead highly recommend getting yourself a copy of the report and getting into the details), but will note that all of these are soft skills – do they have clarity of purpose, do they communicate well, how well do they manage conflict. So investing in helping your teams work effectively will significantly increase your chances of success.
The Good Sponsor
The Good Sponsor is the soul of the project. The sponsor breathes life into a project, and without the sponsor there is no project.
The second most important factor is whether there’s a good project sponsor, noting that the most significant difference comes with the move from Mature to Highly Mature:

And what do we mean by a good sponsor – we mean a project lead or SRO that ensures quick and timely decisions, provides a clear inspiring vision, demonstrates imagination and big-picture thinking, and understands what good progress looks like.
In the words of the report: “Improving the skills of the project sponsor is the number-one factor of success – and also the easiest to improve upon, since each project has only one.”
The Good Place
The Good Place is where the sponsor and team work to create the product. It’s made up of the people who support both sponsor and team. These people can be helpful or destructive. It’s imperative that the organization work to improve their skills if a project is to succeed.
And the third most important factor – whether the environment and culture in which the project is being delivered is conducive to project success:

This has less of an impact than good teams and sponsors (as they will be able to overcome any cultural or environmental issues), and is much harder to change. But investing in your people, and in key elements such as decision latency; emotional maturity; clear communications, user involvement and continuous learning, will provide significant benefits.
Takeaway 2 – Small Agile projects are more successful than large Waterfall ones

So Agile projects are half as likely to fail, and more than three times as likely to be successful, however…
We need to be really careful what we mean by an Agile project. Taking a Waterfall project and calling it Agile, or having Agile teams working to an overarching Waterfall project plan will not make the project more successful (and in reality makes it less likely to be successful). Agile projects require a clear focus on the outcome required (over the outputs and plan), and require the entire project (including the project management layer) to operate in an agile way.
And Agile is not a silver bullet – only 40% of Agile projects are successful, meaning that there are much more significant factors. So you are much better off investing in the soft skills of your teams and sponsors than moving to Agile if you want your projects to be more successful.
If you’re looking for something quicker and easier to do than switching to Agile, the size of the project is actually a more significant factor in whether it’s likely to be successful:

Small projects are 10 times more likely to be successful than grand (enormous) projects, and nearly 8 times less likely to fail. So if you can break up your monster project into a series of smaller projects, you’ll immediately and dramatically increase your chances of success.
Takeaway 3 – skills, tooling, and clarity and completeness of requirements are not indicators of success
You can forget about tools, processes, oversight, management structures, compliance issues, and anything else not associated with [the 6 factors of success]. In fact, don’t change anything. Just work on improving these factors, and everything else will take care of itself.
Surprisingly, these are not factors for project success, and in many cases will actually make you less successful:
- The “skill” of the project manager at managing projects. What’s important are the softer skills – building effective teams, ensuring good decisions are made promptly, and ensuring there is a clear direction. Adherence to any particular methodology (Agile or Waterfall) makes projects less likely to be successful, as the focus becomes on doing it right, rather than doing what’s right.
- The use of project management tools. Introducing JIRA, or Teams, or Project Online, or whatever the latest tool of the month is will not make you more successful. Empowering teams, enabling them to choose the right tool for the job, will.
- The clarity of project objectives or the completeness of requirements. Locking these down early will make you less successful, as this is done at a time when you know least. Projects that are constantly exploring and evolving a clear understanding of what they’re trying to achieve and how they’re planning to do it are those that end up being successful.
Takeaway 4 – if you fix one thing, fix your decision latency
If we were to identify one root cause of software project failures it would be slow decision latency

Decision latency is a skill that underpins all three of the top factors of success – the good team, sponsor and place. Improving it will increase your project success rate from 21% to 75% (3.5 times).
It will also save you a huge amount of time and money – the evidence shows that projects with good decision latency spend about 10% of their budget on decisions, compared to projects with poor decision latency which can spend up to 50% of their budget on decisions.
From the report:
We have discovered that a project will create one decision for every $1,000 in labour costs – i.e. 1,000 decisions for every $1 million of labour. The cost of an average one-hour decision is about £100 – at this speed decisions will consume 10% of the project budget. However, if decisions take four hours, you will spend as much time and money making decisions as you do delivering the project.
And the evidence shows that quicker decisions are not worse than slower decisions. In fact, organisations with an average decision latency of more than three hours are likely to reverse or revisit about 40% of their decisions, meaning 1,000 decisions become more than 2,200.
Conclusions
Firstly, it’s worth reflecting on why the Standish Group stopped publishing the Chaos report. In their words:
It is time to STOP doing software development and implementation “projects” – and start simply developing and implementing software. We know we are going to spend money on developing and implementing software. That is a given. What we need to stop doing is
artificially breaking software into “projects” with all their overhead and waste of time and money. As Nike says, ‘Just Do lt.” Start running – half a mile today, a mile tomorrow. That’s how you improve.
In our words – what they realised was that the entire concept of a project was now holding back software delivery. What was needed was a new paradigm built around teams with ownership of systems and user needs. Agility without the project constraint, delivered through product- and service-orientated organisations.